ABSTRACT
For a long time, the Catholic Church, Nakuru Diocese has been facing the challenge of not
achieving intended goals of their projects due to the over runs in time and budgets in most
Catholic Churches’ projects, it become necessary to examine the influence of project
management practices on project outcomes at catholic churches. The study was therefore
carried out to establish the influence of selected project management practices on project
outcomes at Catholic Churches Nakuru diocese, Nakuru County, Kenya. Specific objectives
included; to establish the influence of Stakeholder participation on project outcomes at
Catholic Churches in Nakuru county; to find out the influence of Project resource planning on
project outcomes at Catholic Churches in Nakuru county; to examine the influence of project
leadership on project outcomes at Catholic Churches in Nakuru county, to investigate the
influence of Project control and evaluation on project outcomes at Catholic Churches Nakuru
county. This study employed descriptive survey design. The target population comprised
three projects, that is; rehabilitation of street children project, (Mwangaza street children
rehabilitation project), Rehabilitation of commercial sex workers project (Women of destiny)
and Integrated programs for the handicapped with a total of 162 staff including project
management staff, project non-management staff and Church project planning and
Development office staff. The research utilized stratified random sampling to select a sample
size of 115 respondents. Structured Questionnaires were used to collect information from the
sampled respondents. Data collected was checked for completeness and thereafter coded and
entered into SPSS version 22 for analysis. Both descriptive and inferential statistics were
used in data analysis. For descriptive statistics, mean, standard deviation, frequency,
percentages were employed while for inferential analysis bivariate Pearson correlation
coefficient and Multi regression analysis were used. Data was presented using tables and
associated explanations. It was established that all the selected project management practices
that included: project resource planning, project leadership, stakeholder involvement and
project monitoring and evaluation had positive significant influence on project outcomes at catholic churches in Nakuru County, Kenya.
KAGUNYA, J (2021). Management Practices And Project Outcomes Of Selected Projects At Catholic Churches In Nakuru County, Kenya. Afribary. Retrieved from https://tracking.afribary.com/works/management-practices-and-project-outcomes-of-selected-projects-at-catholic-churches-in-nakuru-county-kenya
KAGUNYA, JAMES "Management Practices And Project Outcomes Of Selected Projects At Catholic Churches In Nakuru County, Kenya" Afribary. Afribary, 26 May. 2021, https://tracking.afribary.com/works/management-practices-and-project-outcomes-of-selected-projects-at-catholic-churches-in-nakuru-county-kenya. Accessed 15 Nov. 2024.
KAGUNYA, JAMES . "Management Practices And Project Outcomes Of Selected Projects At Catholic Churches In Nakuru County, Kenya". Afribary, Afribary, 26 May. 2021. Web. 15 Nov. 2024. < https://tracking.afribary.com/works/management-practices-and-project-outcomes-of-selected-projects-at-catholic-churches-in-nakuru-county-kenya >.
KAGUNYA, JAMES . "Management Practices And Project Outcomes Of Selected Projects At Catholic Churches In Nakuru County, Kenya" Afribary (2021). Accessed November 15, 2024. https://tracking.afribary.com/works/management-practices-and-project-outcomes-of-selected-projects-at-catholic-churches-in-nakuru-county-kenya